Progress

Project Update 2021-07-26

RAPID CITY, S.D. – July 26, 2021 – Gravel placement is in progress moving east from Highway 385. Please use extreme caution as trucks will be entering the project from Highway 385. Roadway excavation and storm sewer installation continue from Highway 385 to the westernmost Spring Creek bridge. Topsoil is also being placed at various…

Project Update 2021-07-19

RAPID CITY, S.D. – July 19, 2021 – Gravel placement is in progress moving east from Highway 385. Please use extreme caution as trucks will be entering the project from Highway 385. Roadway excavation and storm sewer installation continue from Highway 385 to the westernmost Spring Creek bridge. Topsoil is also being placed at various…

Project Update 2021-07-12

RAPID CITY, S.D. – July 12, 2021 – Roadway excavation and storm sewer installation continue from Highway 385 to the westernmost Spring Creek bridge. Gravel placement is in progress moving towards Spring Creek Trailhead Rd. Topsoil is also being placed at various locations. Culvert and storm sewer installation continues near Victoria Lake Road.  Roadway excavation…

Project Update 2021-07-08

RAPID CITY, S.D. – July 7, 2021 – Roadway excavation and culvert installation continue from Highway 385 to the westernmost Spring Creek bridge. Gravel placement is anticipated to begin late next week. Culvert and storm sewer installation continues moving near Victoria Lake Road.  Roadway excavation and fill placement also continue along the new alignment from…

Project Update 2021-06-28

RAPID CITY, S.D. – June 28, 2021 – Roadway excavation and culvert installation continue from Highway 385 to the westernmost Spring Creek bridge. Gravel placement is anticipated to begin late this month. Storm sewer installation continues moving east from Victoria Lake Road.  Roadway excavation and fill placement also continue along the new alignment from Old…

Project Update 2021-06-21

RAPID CITY, S.D. – June 21, 2021 – Roadway excavation and culvert installation continue from Highway 385 to the westernmost Spring Creek bridge. Gravel placement is anticipated to begin late this month. Storm sewer installation continues moving east from Victoria Lake Road to Stirrup Court. Roadway excavation and undercutting continue near Old Sheridan Road, moving…

Project Update 2021-06-14

RAPID CITY, S.D. – June 14, 2021 – Roadway excavation and culvert installation continue from Highway 385 to the westernmost Spring Creek bridge. Gravel placement is anticipated to begin late this month. Storm sewer installation continues moving east from Victoria Lake Road to Stirrup Court. Storm sewer will be installed across the Stirrup Court approach…

Project Update 2021-06-08

RAPID CITY, S.D. – June 7, 2021 – Roadway excavation and culvert installation continue from Highway 385 to the westernmost Spring Creek bridge. Storm sewer installation continues moving east from Victoria Lake Road to Stirrup Court. Storm sewer will be installed across the Stirrup Court approach this week. Roadway excavation and undercutting continue near Victoria…

Project Update 2021/05/24

RAPID CITY, S.D. – May 24, 2021 – Oftedal Construction will work through Friday of this week and will suspend work over the Memorial Day weekend. A crew will remain on the project to maintain the driving lanes Saturday through Monday. The forecast indicates rain is likely again this week; proceed with caution during precipitation…