Progress

Project Update 2022-05-24

RAPID CITY, S.D. – The sand seal will be installed late this week on the asphalt paving from Victoria Lake Road to Rockwood Road. Gravel will be placed next week starting at the easternmost Spring Creek Bridge moving east. Excavation, slope finishing, topsoil placement, seeding, pipe installation, and fence work will continue in the construction…

Project Update 2022-05-17

RAPID CITY, S.D. – The sand seal for the recently placed asphalt paving from Victoria Lake Road to Rockwood Road will be installed late this week. Additional excavation, slope finishing, topsoil placement, and pipe installation continue in the construction areas west of Rockwood Road. Between Rockwood Road and the easternmost Spring Creek Bridge, the road…

Project Update 2022-05-10

RAPID CITY, S.D. – Asphalt paving from Victoria Lake Road and Rockwood Road continues this week. Paving tie-ins at various approaches and intersecting streets will follow. Additional excavation, slope finishing, and pipe installation continue in the construction areas west of Rockwood Road. Between Rockwood Road and the easternmost Spring Creek Bridge, the road consists of…

Project Update 2022-05-03

Work between Victoria Lake Road and Rockwood Road will begin this week in preparation for asphalt paving, which includes dirt work at the guardrail end sections and street sweeping. The top lift of asphalt is expected to be placed late this week. Additional excavation, slope finishing, and pipe installation continue in the construction areas west…

Project Update 2022-04-26

RAPID CITY, S.D. – Pipe installation and dirt work continue in the construction areas west of Rockwood Road. Work between Victoria Lake Road and Rockwood Road will begin this week in preparation for asphalt paving. The top lift of asphalt is expected to be placed the first week of May. Between Rockwood Road and the…

Project Update 2022-04-12

RAPID CITY, S.D. – Construction operations consist of dirt moving and pipe installation in the construction area west of Rockwood Road. The current focus remains in areas of large fill and locations where driveways require realignment. Between Rockwood Road and the easternmost Spring Creek bridge, the road consists of dirt grade. Motorcycles and 2-wheel drive…

Project Update 04-04-2022

RAPID CITY, S.D. – April 4, 2022 – Dirt moving operations and pipe installation will continue in the construction area, west of Rockwood Lane. The current focus is in areas of large fill and in locations where driveways require re-alignment. Between Rockwood Road and the easternmost Spring Creek bridge, the road consists of dirt grade.…

Project Update 2022-03-28

RAPID CITY, S.D. – March 28, 2022 – Dirt moving operations and pipe installation will continue in the construction area, west of Rockwood Lane. Between Rockwood Road and the easternmost Spring Creek bridge, the road consists of dirt grade. Motorcycles and 2-wheel drive vehicles should consider an alternate route. During inclement weather blading and road…

Project Update 2022-03-21

RAPID CITY, S.D. – March 21, 2022 – Dirt moving operations and pipe installation will continue in the construction area, west of Rockwood Lane. Blasting will take place Tuesday, March 22, 2022, between 8:00 and 9:00 am. approximately 1000′ east of the easternmost Spring Creek Bridge. Expect 15-minute delays during blasting operations. Between Rockwood Road…

Project Update 2022-03-14

RAPID CITY, S.D. – March 14, 2022 – Dirt moving operations will continue in the construction area, west of Rockwood Lane. Blasting is anticipated to take place this week approximately 1000′ east of the easternmost Spring Creek Bridge. Expect 15-minute delays during blasting operations. No Dumping is allowed on any of the slash piles within…

Loading…

Something went wrong. Please refresh the page and/or try again.


Follow Progress

Get new content delivered directly to your inbox.

%d bloggers like this: