Project Update 2021-11-22

RAPID CITY, S.D. – November 22, 2021 – SHERIDAN LAKE ROAD IS OPEN, from Highway 385 to Rapid City. Oftedal will have crews on site this week installing fence and finishing striping and sign installation. No work will take place over the Thanksgiving holiday weekend. General cleanup will be completed next week. Weekly updates will…

Project Update 2021-11-15

RAPID CITY, S.D. – November 15, 2021 – Traffic is on the new alignment from Highway 385 to North Beach Road. The striping and permanent signing will be installed this week, pending weather, from North Beach Road to the western most Spring Creek Bridge. Guardrail will also be completed this week. Reminder: No through traffic…

Project Update 2021-11-08

RAPID CITY, S.D. – November 8, 2021 – Traffic is on the new alignment from Highway 385 to North Beach Road. The striping and permanent signing will be installed this week, pending weather, from North Beach Road to the western most Spring Creek Bridge. Reminder: No through traffic on Sheridan Lake Road from Taylor Ranch…

Project Update 2021-11-01

RAPID CITY, S.D. – November 1, 2021 – Traffic is on the new alignment from Highway 385 to North Beach Road. The asphalt sand seal, striping, and permanent signing will begin late this week, pending weather, from North Beach Road to the western most Spring Creek Bridge. Reminder: Sheridan Lake Road is closed from Taylor…

Project Update 2021-10-25

RAPID CITY, S.D. – October 25, 2021 – Traffic is on the new alignment from Highway 385 to North Beach Road. The asphalt sand seal, striping, and permanent signing will begin this week, pending weather, from North Beach Road to the western most Spring Creek Bridge. Reminder: Sheridan Lake Road is closed from Taylor Ranch…

Project Update 2021-10-11

RAPID CITY, S.D. – October 11, 2021 – Traffic is on the new alignment from Highway 385 to North Beach Road. Asphalt paving will continue as weather permits from Dakota Point Road to the western most Spring Creek Bridge. Topsoil placement and approach work continues from Old Sheridan Road to Rockwood Lane. Striping will take…

Project Update 2021-10-04

RAPID CITY, S.D. – October 4, 2021 – Traffic is on the new alignment from Highway 385 to North Beach Road. Asphalt paving will resume mid-week near Dakota Point Road. Gravel placement and approach work continues from Old Sheridan Road to Rockwood Lane. Guardrail installation will begin late this week. Installation of pipe culvert and…

Project Update 2021-09-27

RAPID CITY, S.D. – September 27, 2021 – Sand seal will be applied to the new asphalt from Norseman Lane to Victoria Lake Road this week Removal of the gravel detour to the marina continues. Traffic is on the new alignment road up to North Beach Road. Asphalt Prime is being placed on the gravel…

Project Update 2021-09-20

RAPID CITY, S.D. – September 20, 2021 – Seeding is in progress moving west from Norseman Lane. Finish work behind the curb and on slopes continues. Removal of the gravel detour to the marina will take place this week. Traffic is on the new alignment road up to North Beach Road. Reminder: Sheridan Lake Road…

Project Update 2021-09-13

RAPID CITY, S.D. – September 13, 2021 – Asphalt sand seal will be applied from Norseman Lane to Victoria Lake Road this week. Finish work behind curb and on slopes continues. Curb and gutter continue at various locations from the westernmost Spring Creek Bridge to Dakota Point. Asphalt has begun near Highway 385 and will…