Progress

Project Update 2022-08-04

RAPID CITY, S.D. – Asphalt paving is complete from Rockwood Road to the easternmost Spring Creek Bridge. Construction will be paused through the Sturgis Motorcycle Rally. On Monday, Aug. 15, 2022, construction will resume with an asphalt overlay from the westernmost Spring Creek Bridge to the easternmost Spring Creek Bridge. The speed limit is 35…

Project Update 2022-07-26

RAPID CITY, S.D. – Asphalt paving is complete from Rockwood Road to the easternmost Spring Creek Bridge. Striping and guardrail will be installed this week. Topsoil placement, gravel placement at approaches, and general cleanup continues throughout the work area as well. An asphalt overlay will be placed from the westernmost Spring Creek Bridge to the…

Project Update 2022-07-19

RAPID CITY, S.D. – Asphalt paving will continue this week at the easternmost Spring Creek Bridge. The remaining section of Phase Three is surfaced with the first lift of asphalt as of Monday, July 18, 2022 . The final lift of asphalt will be placed by the end of July. Topsoil placement, temporary seeding, and…

Project Update 2022-07-11

RAPID CITY, S.D. – Asphalt paving will begin this week at the easternmost Spring Creek Bridge. The entire roadway is scheduled to have asphalt surfacing by the end of July. Topsoil placement, temporary seeding, and general cleanup continues throughout the work area as well. The speed limit is 35 mph from Victoria Lake Road to…

Project Update 2022-07-06

RAPID CITY, S.D. – Gravel placement continues in preparation for asphalt paving which will begin early next week at the easternmost Spring Creek bridge. The entire roadway is scheduled to have asphalt surfacing by the end of July. Topsoil placement and general cleanup continues throughout the work area as well. The speed limit is 35…

Project Update 2022-06-28

RAPID CITY, S.D. – Work will continue as scheduled this week through Friday, July 1, 2022. No work will take place over the Fourth of July holiday weekend and Personnel will be onsite to apply dust control measures, as necessary. Gravel placement continues between Rockwood Road and the easternmost Spring Creek Bridge. This entire length…

Project Update 2022-06-21

RAPID CITY, S.D. – Gravel placement continues between Rockwood Road and the easternmost Spring Creek Bridge. This entire length is anticipated to have gravel surfacing by late next week. Topsoil placement and general cleanup continues throughout the work area. Between Rockwood Road and the easternmost Spring Creek Bridge, the road consists of dirt grade. Motorcycles…

Project Update 2022-06-13

RAPID CITY, S.D. – Rain events continue to slow the placement of gravel and topsoil, with normal progress to resume as the project dries and conditions improve. The remaining curb and gutter will be placed this week near the easternmost Spring Creek Bridge. Permanent striping from Dakota Point to the westernmost Spring Creek Bridge will…

Progress Update 2022-06-07

RAPID CITY, S.D. – Recent rain has slowed the placement of gravel, with normal progress to resume as the project dries and conditions improve. Curb and gutter will be placed next week near the easternmost Spring Creek Bridge. Permanent striping from Dakota Point to the westernmost Spring Creek Bridge will take place as well. Between…

Project Update 2022-06-02

RAPID CITY, S.D. – The sand seal will be installed on the asphalt paving from the westernmost Spring Creek Bridge to Dakota Point. Pipe work will be complete this week and grading crews are finishing ditch cuts and the new subgrade. Gravel placement will begin from the easternmost Spring Creek Bridge heading east. Permanent striping…

Loading…

Something went wrong. Please refresh the page and/or try again.


Follow Progress

Get new content delivered directly to your inbox.

%d bloggers like this: