Project Update 2021-01-22

RAPID CITY, S.D. – January 22, 2021 – Oftedal Construction will continue working outside of the existing roadway, from Norseman Lane to Highway 385, in January and February as weather permits. Project updates will only be distributed as needed during this time. Significant construction activities are scheduled to resume in March 2021.   Motorists are…

Project Update 2021-01-12

RAPID CITY, S.D. – January 12, 2021 – Work this week includes fence removal, minor grading, and stump clearing outside of the existing roadway from Norseman Lane to Highway 385. Crews from Pennington County Highway Department will continue removing trees adjacent to Sheridan Lake Road at various locations. This work is expected to continue as…

Project Update 2021-01-04

RAPID CITY, S.D. – January 4, 2021 – Oftedal will resume work this week outside of the existing roadway from Norseman Lane to Highway 385 with fence removal, minor grading, and stump clearing. Crews from Pennington County Highway Department will continue removing trees adjacent to Sheridan Lake Road at various locations. This work is expected…

Project Update 2020-12-22

RAPID CITY, S.D. – December 22, 2020 – Installation of mailboxes and permanent signing from Albertta Drive to Norseman Lane will be complete this week. Work continues outside of the existing roadway from Norseman Lane to Highway 385 with minor grading, and stump clearing. Oftedal intends to work through December 23. Construction work will be…

Project Update 2020-12-15

RAPID CITY, S.D. – December 15, 2020 – Fence work from Albertta Drive to Norseman Lane will be complete this week. Work continues outside of the existing roadway from Norseman Lane to Highway 385 with pipe installation, grading, and clearing. Oftedal intends to work through December 23. Construction work will be shut down December 24,…

Project Update 2020-12-08

RAPID CITY, S.D. – December 8, 2020 – Installation of curve signs should be completed this week from Albertta Drive to Norseman Lane. Work this week includes fencing and mailbox replacement. Work continues outside of the existing roadway from Norseman Lane to Highway 385 with pipe installation, grading, and clearing. Crews from Pennington County Highway…

Project Update 2020-12-02

RAPID CITY, S.D. – December 2, 2020 – Installation of permanent signs should be completed this week from Albertta Drive to Norseman Lane. Work this week also includes fencing and mailbox replacement. Work continues outside of the existing roadway from Norseman Lane to Highway 385 with pipe installation, grading, and clearing. Crews from Pennington County…

Project Update 2020-11-23

RAPID CITY, S.D. – November 23, 2020 – Work from Albertta Drive to Norseman Lane continues with mailbox replacement and installation of permanent signs. Work has begun outside of the existing roadway from Norseman Lane to Highway 385 with pipe installation, grading, and clearing. Crews from Pennington County Highway Department are removing trees adjacent to…

Project Update 2020-11-17

RAPID CITY, S.D. – November 17, 2020 – Work this week includes replacing mailboxes and installing permanent signs. Oftedal also intends to work from Norseman Lane to Highway 385 outside of the existing roadway, as weather allows. That work will include pipe installation, grading, and clearing. Crews from Pennington County Highway Department are removing trees…

Project Update 2020-11-09

RAPID CITY, S.D. – November 9, 2020 – Work this week includes replacing mailboxes and installing permanent signs. Oftedal also intends to work from Norseman Lane to Highway 385 outside of the existing roadway, as weather allows. That work will include pipe installation, grading, and clearing. Motorists are asked to be aware of suddenly slowing…