Progress

Project Update 2021-10-18

RAPID CITY, SD – October 18, 2021 – Traffic is on the new alignment from Highway 385 to North Beach Road. Asphalt paving will continue as weather permits from Dakota Point Road to the western most Spring Creek Bridge. Topsoil placement and approach work continues from Old Sheridan Road to Rockwood Lane. Asphalt paving will…

Project Update 2021-10-11

RAPID CITY, S.D. – October 11, 2021 – Traffic is on the new alignment from Highway 385 to North Beach Road. Asphalt paving will continue as weather permits from Dakota Point Road to the western most Spring Creek Bridge. Topsoil placement and approach work continues from Old Sheridan Road to Rockwood Lane. Striping will take…

Project Update 2021-10-04

RAPID CITY, S.D. – October 4, 2021 – Traffic is on the new alignment from Highway 385 to North Beach Road. Asphalt paving will resume mid-week near Dakota Point Road. Gravel placement and approach work continues from Old Sheridan Road to Rockwood Lane. Guardrail installation will begin late this week. Installation of pipe culvert and…

Project Update 2021-09-27

RAPID CITY, S.D. – September 27, 2021 – Sand seal will be applied to the new asphalt from Norseman Lane to Victoria Lake Road this week Removal of the gravel detour to the marina continues. Traffic is on the new alignment road up to North Beach Road. Asphalt Prime is being placed on the gravel…

Project Update 2021-09-20

RAPID CITY, S.D. – September 20, 2021 – Seeding is in progress moving west from Norseman Lane. Finish work behind the curb and on slopes continues. Removal of the gravel detour to the marina will take place this week. Traffic is on the new alignment road up to North Beach Road. Reminder: Sheridan Lake Road…

Project Update 2021-09-13

RAPID CITY, S.D. – September 13, 2021 – Asphalt sand seal will be applied from Norseman Lane to Victoria Lake Road this week. Finish work behind curb and on slopes continues. Curb and gutter continue at various locations from the westernmost Spring Creek Bridge to Dakota Point. Asphalt has begun near Highway 385 and will…

Project Update 2021-09-08

Sheridan Lake Road Reconstruction RAPID CITY, S.D. – September 8, 2021 – Asphalt sand seal will be applied from Norseman Lane to Victoria Lake Road this week. Finish work behind curb and on slopes will follow. Topsoil placement continues from Highway 385 to the westernmost Spring Creek bridge. Curb and gutter will also be placed…

Project Update 2021/08/31

RAPID CITY, S.D. – August 31, 2021 – Topsoil placement continues from Highway 385 to the westernmost Spring Creek bridge.  Asphalt prime is being applied from Highway 385 to Dakota Point. Curb and gutter will be placed from Taylor Ranch Road west to Dakota Point as well.  Reminder: Sheridan Lake Road is closed from Taylor…

Project Update 2021-08-23

RAPID CITY, S.D. – August 23, 2021 – Gravel finishing and topsoil placement continues from Highway 385 to the westernmost Spring Creek bridge. Seeding continues this week on the large backslopes. Final preparation for asphalt will take place late this week with asphalt prime being applied from Highway 385 to Dakota Point. Reminder: Sheridan Lake…

Project Update 2021-08-16

RAPID CITY, S.D. – August 16, 2021 – Gravel finishing and topsoil placement continues from Highway 385 to the westernmost Spring Creek bridge. Seeding will begin this week on the large backslopes. Approach, curb, and gutter installation will continue from Victoria Lake Road to the east. Roadway excavation and fill placement continues along the new…

Loading…

Something went wrong. Please refresh the page and/or try again.


Follow Progress

Get new content delivered directly to your inbox.

%d bloggers like this: