Progress

Project Update 2021-04-12

RAPID CITY, S.D. – April 12, 2021 – Patching on portions of the existing asphalt on Sheridan Lake Road will take place this week from the westernmost Spring Creek bridge to easternmost Spring Creek bridge. Excavation for box culvert installation is in progress at the Horse Creek Crossing. Grading and undercutting is in progress from…

Project Update 2021-04-06

RAPID CITY, S.D. – April 6, 2021 – Milling continues on Sheridan Lake Road from Norseman Lane moving west toward Old Sheridan Road. Affected mailboxes will be relocated. The gravel detour to the Marina from Highway 385 is completed and in use. Blasting rock for excavation will continue this week. Work this week also includes…

Project Update 2021-03-30

RAPID CITY, S.D. – March 30, 2021 – Milling on Sheridan Lake Road has begun at Norseman Lane and is moving west. Affected mailboxes will be relocated. The gravel detour to the Marina from Highway 385 is completed and in use. Blasting rock for excavation will continue this week. Work this week also includes earth…

Project Update 2021-03-26

RAPID CITY, S.D. – March 26, 2021 – Milling on Sheridan Lake Road will begin Monday, March 29, 2021, at Norseman Lane and will move west. Affected mailboxes will be relocated. Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction…

Project Update 2021-03-22

RAPID CITY, S.D. – March 22, 2021 – Work resumes this week on the gravel detour to the Marina from Highway 385. Blasting rock for excavation will also continue this week. Work this week also includes earth moving and installing storm sewer in Phase 1. Tree removal continues from Boulder Hill Road to the west.…

Project Update 2021-03-15

RAPID CITY, S.D. – March 15, 2021 –Work on the Sheridan Lake Road Reconstruction Project is suspended early this week due to the winter storm. Oftedal Construction crews will remove snow and maintain access to the Mountain Park Subdivision and Sheridan Lake Marina.  Pennington County crews will remove snow on all other portions of Sheridan…

Project Update 2021-03-09

RAPID CITY, S.D. – March 9, 2021 – Sheridan Lake Road is fully closed from Spring Creek Trailhead Road to Highway 385. It is anticipated to reopen Nov. 19, 2021. Thru traffic from Rapid City to Highway 385 must use an alternate route. Traffic to the Marina will be maintained on salvaged gravel from Highway…

Project Update 2021-03-01

RAPID CITY, S.D. – March 1, 2021 – Oftedal Construction has resumed construction activities on the Sheridan Lake Road Reconstruction project. Sheridan Lake Road is fully closed from Spring Creek Trailhead Road to Highway 385. It is anticipated to reopen Nov. 19, 2021. Thru traffic from Rapid City to Highway 385 must use an alternate…

Sheridan Lake Road Reconstruction Project to Begin March 1

RAPID CITY, S.D. – Beginning Monday, March 1, 2021, Oftedal Construction will resume work on the Sheridan Lake Road reconstruction project from Norseman Lane to Highway 385. Sheridan Lake Road will be fully closed from Spring Creek Trailhead Road to Highway 385 and is anticipated to re-open on Nov. 19, 2021. Thru traffic from Rapid…