Project Update 2022-05-24

RAPID CITY, S.D. – The sand seal will be installed late this week on the asphalt paving from Victoria Lake Road to Rockwood Road. Gravel will be placed next week starting at the easternmost Spring Creek Bridge moving east.

Excavation, slope finishing, topsoil placement, seeding, pipe installation, and fence work will continue in the construction areas west of Rockwood Road.

Between Rockwood Road and the easternmost Spring Creek Bridge, the road consists of dirt grade. Motorcycles and two-wheel drive vehicles should consider an alternate route. During inclement weather, slippery and muddy road conditions may exist.

The speed limit is 35 mph from Victoria Lake Road to the easternmost Spring Creek Bridge. Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lanes.

Additional information will be provided as phasing, access, and traffic control changes with the progression of the project. To view the entire scope of the project, with phasing and traffic control plans, please visit the project website: https://www.SheridanLakeRoad.com or the ArcGIS StoryMap located at: https://arcg.is/58fn9. The public can also follow the project on Facebook, “Sheridan Lake Road Reconstruction,” and on Twitter, “Sheridan Lake Road Reconstruction@FerbEng.” The public may leave a message at 605-343-3311 with any questions or concerns regarding this reconstruction project.

Roadway excavation on Sheridan Lake Road, 
Monday, May 23, 2022, Rapid City, SD
Roadway excavation on Sheridan Lake Road,
Monday, May 23, 2022, Rapid City, SD

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: