Project Update 2022-03-14

RAPID CITY, S.D. – March 14, 2022 – Dirt moving operations will continue in the construction area, west of Rockwood Lane. Blasting is anticipated to take place this week approximately 1000′ east of the easternmost Spring Creek Bridge. Expect 15-minute delays during blasting operations.

No Dumping is allowed on any of the slash piles within the project area.                                                 

During inclement weather, blading and road surface maintenance will be completed, but road conditions may be slippery and muddy.

The speed limit is 35 MPH from Victoria Lake Road to the easternmost Spring Creek Bridge. Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lanes.

Additional information will be provided as phasing, access, and traffic control changes with the progression of the project. To view the entire scope of the project, with the phasing and traffic control plans, please visit the project website https://www.SheridanLakeRoad.com or the ArcGIS StoryMap located at: https://arcg.is/58fn9. Interested persons can also follow the project on Facebook, “Sheridan Lake Road Reconstruction,” and on Twitter, “Sheridan Lake Road Reconstruction@FerbEng.” The public may leave a message at (605)343-3311 with any questions or concerns regarding this reconstruction project.

Dirt moving operation on Sheridan Lake Road, Rapid City, South Dakota
Dirt moving operation on Sheridan Lake Road, Rapid City, South Dakota

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: