RAPID CITY, S.D. – August 31, 2021 – Topsoil placement continues from Highway 385 to the westernmost Spring Creek bridge.  Asphalt prime is being applied from Highway 385 to Dakota Point. Curb and gutter will be placed from Taylor Ranch Road west to Dakota Point as well. 

Reminder: Sheridan Lake Road is closed from Taylor Ranch Road to Highway 385.

Roadway excavation and fill placement continues along the new alignment from Old Sheridan Lake Road moving west to Rockwood Road. Topsoil and rock picking is also being completed from Norseman Lane to Victoria Lake Road.  Asphalt paving will continue this week moving west towards Victoria Lake Road.

A maintenance crew will be onsite during precipitation events and through the weekends to continue to maintain the road.

Traffic to the Marina at Sheridan Lake Road must use the gravel detour from Highway 385 until asphalt paving is placed.

The speed limit is 35 mph from Norseman Lane to Rockwood Road. Sheridan Lake Road is fully closed from Spring Creek Trailhead Road to Highway 385. Thru traffic from Rapid City to Highway 385 must use an alternate route. Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lanes.

Additional information will be provided as phasing, access, and traffic control changes with the progression of the project. To view the entire scope of the project, with the phasing and traffic control plans as well as weekly updates, please visit the project website https://www.SheridanLakeRoad.com or the ArcGIS StoryMap located at: https://arcg.is/58fn9. Interested persons can also follow the project on Facebook, “Sheridan Lake Road Reconstruction,” and on Twitter, “Sheridan Lake Road Reconstruction@FerbEng.” The public may leave a message at (605)343-3311 with any questions or concerns regarding this reconstruction project.

Asphalt Prime Placement on Sheridan Lake Road, Pennington County, South Dakota, Monday, August 31, 2021.
Asphalt Prime Placement on Sheridan Lake Road, Pennington County, South Dakota, Monday, August 31, 2021.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: