Project Update 2020-09-03

RAPID CITY, S.D. – September 3, 2020 – Finish grading is taking place from Clarkson Road to Jasmine Lane. Gravel placement will continue this week moving west toward Jasmine Lane. Storm sewer installation continues near Norseman Lane. Curb and gutter installation is continuing this week and concrete fillets will be placed at Countryside Boulevard.

Traffic delays are anticipated to remain approximately 15 minutes during daylight hours as traffic is reduced to a single lane and guided through the work zone with the use of flaggers and a pilot car. Plan accordingly and add 15 minutes, at a minimum, to travel schedules. The pilot car will accommodate school buses to minimalize delays and bus stop locations will be maintained to assure safety of the students. In an effort to maintain the construction schedule and timely completion of the project, work hours will continue to be daylight hours until winter shutdown.

Completing curb on Sheridan Lake Road from east of Clarkson Road to Albertta Drive 2020-08-31
Completing curb on Sheridan Lake Road, east of Clarkson Road to Albertta Drive 2020-08-31
Grading Sheridan Lake Road from Spring Canyon Trail toward Norseman Lane 2020-08-31
Grading Sheridan Lake Road from Spring Canyon Trail toward Norseman Lane 2020-08-31

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: