Project Update 2020-06-02

RAPID CITY, S.D. – June 2, 2020 – Cold milling and reclaim work will continue from Albertta Drive and Norseman Lane. Traffic is reduced to a single lane and guided through the work zone with the use of flaggers and a pilot car. Traffic delays are expected to be 15 minutes. Flaggers are stationed at the ends of the milling work zone and at intersecting streets. Residents with access directly onto Sheridan Lake Road will be notified when the milling operation will occur near their driveways. The cold milling operation is expected to be complete by June 6, 2020.

Storm sewer crews will begin work the week of June 8, at Albertta Drive.

Utility relocation activities continue to progress along Sheridan Lake from Clarkson Road to Norseman Lane.

Tree removals and cleanup will continue this week along Sheridan Lake Road.

Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lanes. Additional information will be provided as phasing, access, and traffic control changes with the progression of the project.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: