Sheridan Lake Road Reconstruction

Project Location

Reconstruction from Junction of US 385 to Albertta Drive in Rapid City, Pennington County, South Dakota

For detailed project information, visit the Story Map:

Story Map

Description

The primary purpose of this reconstruction project is to improve safety for the traveling public and improve the operational efficiency of Sheridan Lake Road.

The project includes grading, asphalt, curb and gutter, grading for sidewalk and storm sewer.Increase lane widths and added shoulders. The urban section will have three 12-foot lanes with curb and gutter and grading for sidewalk on the south side of the roadway from Spring Canyon Trail to Albertta Drive. The rural sections of the project will be primarily two 12-foot lanes with four foot shoulders, some short sections may require curb and gutter due to steep back slopes. Horizontal and vertical curves will meet 50 mph design speeds where feasible.

Contract

  • Prime Contractor: Oftedal Construction, Inc.
  • Contract Amount: $22.9 million
  • Contract Completion Date: July 1, 2022
Sheridan Lake Road road sign

Latest Progress

Project Update 2020-06-29

RAPID CITY, S.D. – June 29, 2020 – Two-way traffic will be maintained through the holiday weekend. Through traffic, such as motorists on their way to Sheridan Lake, are advised to consider an alternate route. Traffic delays are 15 minutes…

Project Update 2020-06-22

RAPID CITY, S.D. – June 22, 2020 – Milling will resume late this week at Clarkson Road, moving west. Storm sewer installation continues this week moving west from Albertta Drive. Utility relocation activities continue to progress along Sheridan Lake from…

Project Update 2020-06-16

RAPID CITY, S.D. – June 16, 2020 – Through traffic, such as motorists on their way to Sheridan Lake, are advised to consider an alternate route. Traffic delays are 15 minutes during daylight hours, when traffic is reduced to a…